Setting the Cleanup Schedule and Data Retention
Setting the Cleanup Schedule and Data Retention
You can configure the cleanup schedule and set the duration for data retention.
Setting the cleanup run for a single time
1. | In the Project Console, select the Control panel button. |
The Control panel displays.
Settings the clean-up to run multiple times per occurence
4.2. | In the Cleanup page, select Ctrl or Shift to select multiple values. |
You can select multiple values to schedule your cleanup for every Day, Week, Month, and Year—for instance, schedule cleanup daily at 4:10, 4:20, 8:10, and 8:20.
Setting data age retention
When a cleanup check happens, it removes all data older than a certain age. You can set your flow run's maximum data retention period per status. You can specify the age to retain the data and documents generated by the flow run.
By default, we set all finished runs to clean up if they're older than 90 days.